Protection Relay Testing Procedure: Secondary & Primary Injection (87T, 67, 50BF) Q&A

15 Relay Testing Procedure Q&A – Injection & Verification

Learn primary and secondary injection, relay pickup and timing, differential and directional tests, breaker failure and safe restoration. These interview answers are for study; actual testing requires authorized personnel, an approved outage and the specific relay manual. Try both mock tests after reading the answers.

Jump to Question:
01

Q1. What is the difference between primary injection testing and secondary injection testing?

Answer: Primary injection testing applies a controlled test current to the primary circuit of an isolated current transformer (CT) or circuit breaker. It can verify the CT ratio, polarity, secondary wiring and relay response as one chain. If the trip path is included in the approved test, it can also verify breaker operation. Secondary injection applies a known current or voltage directly to the relay inputs through an approved test interface. It checks relay pickup, operating time, logic and output contacts without passing high current through the primary circuit. For example, a 400/1 A CT should ideally produce 1 A secondary at 400 A primary. Secondary injection alone cannot prove that the installed CT ratio or field wiring is correct. Both tests serve different purposes.

Read detailed article
02

Q2. What is the step-by-step procedure for performing a secondary injection test?

Answer: Start with the approved test plan, relay manual, wiring diagram and latest setting file. Only trained, authorized staff should test an isolated panel under a valid permit and LOTO. Confirm the absence of hazardous energy and prevent unintended trips or closing of other breakers. Use the correct test block to secure CT secondary shorting before disconnecting relay current inputs, and isolate VT sources to prevent backfeed. With test outputs off, connect the calibrated kit to the isolated relay inputs and the designated trip contact to its compatible binary input. Confirm the 1 A or 5 A rating, channel mapping and active setting group. Apply the approved test points, record pickup and time, then switch off injection and complete the controlled restoration checklist.

Read detailed article
03

Q3. How do you perform pickup, drop-off, and timing tests on a numerical overcurrent relay?

Answer: Pickup is the current at which the selected overcurrent element starts. Drop-off is the current at which it resets when current falls. In a safe test setup, observe the relay start signal while the test kit slowly increases current from below the approved setting. Then reduce current and record the reset value. For example, a 1 A relay element set to 1.2 A should start close to 1.2 A within its stated tolerance. The drop-off value depends on the relay reset ratio and algorithm. For a timing test, begin from a reset condition and apply a specified current step. Measure the time from injection to the selected operate output. Compare all results with the manufacturer limits, including reset and timer behavior.

Read detailed article
04

Q4. How do you verify inverse-time (51) and definite-time curves using a relay test kit?

Answer: First confirm the active current setting, curve type, time multiplier setting (TMS) and definite-time delay. An inverse-time relay operates faster as the fault current increases. A definite-time element normally keeps the same set delay once current is above pickup. In an isolated test setup, select several current multiples allowed by the relay and test kit, such as two, three and five times pickup. For a 1 A pickup and an injected current of 3 A, the plug setting multiplier (PSM) is 3. Calculate the expected time from the selected curve or relay software and compare it with the measured time. Allow full reset between shots and check other stages do not affect results. Use the specified timing tolerance, not a universal percentage.

Read detailed article
05

Q5. How do you test 50N/51N earth-fault pickup and operating time on site?

Answer: Earth-fault elements 50N and 51N normally respond to residual or neutral current. Confirm whether the relay calculates residual current from three phase CTs or measures a separate neutral input. Also check whether the settings use residual current (3I0) or zero-sequence current (I0). In the approved isolated test arrangement, apply the specified residual current using the correct test kit channels. Observe start pickup, then apply the selected test points to measure the trip time. For 50N, verify the high-set stage and any configured delay. For 51N, compare the time with its selected inverse or definite-time characteristic. Check alarm and trip indications against the wiring diagram. A separate primary or wiring test is needed to prove the actual CT circuit and its polarity.

Read detailed article
06

Q6. How do you test an 87T transformer differential relay (pickup, bias slope, 2nd harmonic restraint)?

Answer: An 87T relay compares currents entering and leaving a transformer after ratio and phase-angle compensation. Before testing, confirm the transformer vector group, CT ratios, winding ratings and differential settings. A suitable multi-channel test kit can simulate balanced through-current and internal fault current in an isolated relay. The balanced case should remain stable. For pickup and bias slope, test points on both sides of the manufacturer operating characteristic at selected restraint currents. For second-harmonic restraint, where enabled, use a waveform with controlled fundamental and second-harmonic components to check blocking or restraint and release near the configured threshold. Some modern relays use other inrush detection methods. Verify the correct element operates and record the measured characteristic rather than assuming every relay uses the same bias formula.

Read detailed article
07

Q7. How do you check stability and operating zones of ANSI 64REF (Restricted Earth Fault) protection?

Answer: Restricted earth fault (REF) protection detects earth faults within a defined winding zone between the phase CTs and neutral CT. Start by identifying whether the scheme uses high-impedance or low-impedance REF. Their test methods and required test equipment are different. In an approved isolated setup, simulate an external earth fault using the manufacturer's current relationships so the phase residual current and neutral current balance correctly. The REF element should remain stable. Next simulate an internal earth fault with the specified differential current relationship and verify pickup and operation. Compare the measured results with the relay settings and test tolerances. High-impedance schemes also require checks of their stabilizing circuit. A successful secondary test does not replace CT polarity, ratio and field wiring verification.

Read detailed article
08

Q8. How do you verify the direction and Maximum Torque Angle (MTA) of ANSI 67 and 67N relays?

Answer: ANSI 67 is directional phase overcurrent protection, while 67N is directional earth-fault protection. Both need current and a suitable reference or polarizing quantity to determine fault direction. The maximum torque angle (MTA), sometimes called relay characteristic angle, is related to the most sensitive operating direction. Confirm the relay angle convention, phase sequence, CT/VT polarity and polarizing method before testing. A calibrated multi-channel test kit can apply representative forward and reverse fault phasors in a controlled, isolated setup. At a suitable test current above pickup, verify the forward direction permits operation and the reverse direction is blocked for a forward-only stage. Check angular boundaries against the configured characteristic. Residual voltage and current conventions for 67N must match the specific relay manual.

Read detailed article
09

Q9. How do you test the ANSI 50BF breaker-failure sequence and timer?

Answer: Breaker failure protection provides backup if a breaker does not clear a fault after a trip command. First review the approved logic, initiating trip signal, current threshold, breaker position inputs and timer settings. Isolate all actual upstream trip outputs and automatic closing paths before using a breaker simulator or relay test kit. A failed-breaker test represents a valid trip initiation with fault current continuing and, where used by the logic, a closed 52a status. Observe the retrip and backup trip indications and measure their configured delays. A successful-breaker test represents current interruption and the required open status before timeout; the backup trip should not operate. Some schemes use current-only or contact-based criteria. Verify the actual configured logic and never simulate failure on an uncontrolled live trip circuit.

Read detailed article
10

Q10. How do you test motor protection relay elements (49 cold/hot curve, 51LR, 46)?

Answer: ANSI 49 protects a motor against overheating using a thermal model. Its operating time depends on current and the estimated temperature or thermal capacity already used. For cold and hot tests, prepare the specified initial thermal states in an isolated relay and compare operating times with the configured thermal curve. A hot motor generally has less remaining thermal capacity. ANSI 51LR protects against locked rotor or prolonged high current, depending on the relay design. Test the required starting or running logic and delay. ANSI 46 responds to negative-sequence current caused by imbalance. Use controlled three-phase test quantities to verify its pickup and timing. Record the thermal state, start conditions and negative-sequence values. Use the motor data and relay manual, not arbitrary current settings.

Read detailed article
11

Q11. How do you test 27 (undervoltage), 59 (overvoltage), and 81 (frequency) relays?

Answer: Voltage and frequency functions are checked using a calibrated voltage source in the isolated relay test arrangement. Confirm the voltage rating, nominal frequency, phase-to-phase or phase-to-neutral measurement and the enabled phase logic. ANSI 27 starts when the measured voltage falls below its setting, while 59 starts when voltage rises above its setting. Apply approved values around each threshold and verify pickup, reset and operating time. ANSI 81 checks frequency; underfrequency and overfrequency stages respond on opposite sides of their configured limits. For example, a 50 Hz system may have separate underfrequency and overfrequency stages defined by its protection study. Confirm voltage supervision and any blocking conditions before measuring frequency operation. Record the actual values and compare with the relay's stated tolerances.

Read detailed article
12

Q12. How do you test Zone 1, Zone 2, and Zone 3 reach of a distance relay (ANSI 21)?

Answer: A distance relay calculates apparent impedance from voltage and current for the selected fault loop. Its zones have different reach and time settings. Load the approved line data, CT and VT ratios, zone characteristics and earth compensation into the test plan. A multi-channel relay test kit can simulate fault loop impedances on both sides of each zone boundary while the relay is safely isolated. Check the zone indication and operating time at each point. For example, an apparent loop voltage of 10 V and loop current of 2 A gives 5 ohms in secondary quantities. The actual zone reach must be converted to the correct basis. Allow for overlapping zones and check the relevant stage output, reverse direction and blocking logic where configured.

Read detailed article
13

Q13. How do you test ANSI 25 synchrocheck permissive limits and ANSI 79 auto-reclose timers?

Answer: ANSI 25 checks whether two electrical systems are suitable for connection. In an isolated test setup, a suitable kit represents the two voltage sources. Verify the permitted and blocked conditions for voltage difference, frequency difference and phase-angle difference, using the configured logic and limits. Check any separate live-bus or dead-bus conditions as specified. ANSI 79 controls automatic breaker reclosing after selected trips. With actual closing and trip circuits isolated, use a breaker simulator to verify the programmed dead time, reclaim time, number of attempts and lockout or blocking conditions. Also verify that synchrocheck permission is required where the scheme specifies it. Record the complete timing sequence and the final relay state. Never test automatic closing against an uncontrolled live breaker.

Read detailed article
14

Q14. How do you perform CT ratio, PT ratio, and circuit breaker opening time measurements?

Answer: These measurements require suitable test equipment, an approved outage and verified isolation. A CT ratio test compares primary and secondary current, or uses a dedicated CT analyzer following its approved method. For a 400/5 A CT, the rated ratio is 80:1. A PT or VT ratio test compares primary and secondary voltage with a suitable ratio tester; prevent unintended backfeed because secondary excitation can produce hazardous primary voltage. Circuit breaker opening time is measured using a breaker timing analyzer and the specified auxiliary supply, with stored-energy and movement hazards controlled. Compare the interval from the opening command to main contact separation for each pole against the manufacturer data. Record pole spread, test conditions and results. These checks complement relay injection testing.

Read detailed article
15

Q15. What restoration checks are required after testing (and what happens if a CT shorting link is left closed)?

Answer: Restoration is as important as testing. Stop and disconnect the test sources according to the approved procedure. Verify the CT secondary circuit is continuous and correctly connected before authorized staff remove temporary CT shorting links on in-service cores. A link left closed across a working CT circuit can bypass the relay input, causing low or zero measured current and possible protection failure. Unused CT cores must retain their required shorting and grounding. Restore VT links, DC supplies, trip circuits, communication paths, automatic functions and the correct setting group. Remove test mode, temporary blocks and simulated inputs as authorized. Confirm healthy indications, correct meter readings and trip circuit supervision. Complete an independent restoration check, record the results and obtain permission before returning the equipment to service.

Read detailed article

Test Your Knowledge Through Mock Test

Secondary & Primary Injection Testing · Two tests, 10 questions each. Choose a test below to begin.

Question 1 of 100 / 10 answered

Your answers stay on this page.

KEEP LEARNING WITH ELECTRICAL TOPIC

Learn Faster. Improve Your Electrical Skills.

WEBSITE • EMAIL UPDATES

New guides. Straight to your inbox.

Subscribe free. Get fresh website updates.