AC Motor Starter Practical & Maintenance Interview Questions – Star-Delta Wiring, Timer & Interlocking Tests

10 AC Motor Starter Interview Q&A – Practical & Maintenance Part 2

Read short, practical answers. Then try two mock tests.

Jump to Question:
11

Q11. How do you verify a motor's six winding leads and nameplate suitability before star-delta connection?

Answer: Confirm that both ends of each motor winding are available and correctly identified before using a star-delta starter. Typical markings are U1, V1, W1 and U2, V2, W2, and the delta voltage rating must suit the measured line supply. Check isolated winding identification against the motor diagram and investigate any unclear markings before connection.

Read detailed article
12

Q12. How do you check a star-delta starter's power and control wiring against the circuit diagram?

Answer: Compare each power conductor and control wire with the approved diagram, including terminals, coil returns and protective contacts. This may include A1–A2 coil connections, 95–96 overload continuity and the NC cross-interlocks between star and delta contactors. Record drawing discrepancies and close them before performing the authorised functional test.

Read detailed article
13

Q13. How do you verify the main, star and delta contactor operating sequence?

Answer: Verify that the main and star contactors operate first, then star opens before delta closes, while main stays on. The star period and the break-before-make interval are separate settings or characteristics, often expressed in seconds and milliseconds respectively. Confirm the actual order and transition from the indicators or an approved test record.

Read detailed article
14

Q14. How do you select and verify the star-to-delta changeover time during commissioning?

Answer: Set changeover from the motor's acceleration behaviour and the mechanism's ability to carry the load in star. A 5–15 second star period may be a starting reference on some applications, but load inertia and manufacturer limits govern the final setting. Review current and speed at transfer and record the approved timer value.

Read detailed article
15

Q15. How do you check the electrical and mechanical interlocks of a star-delta starter?

Answer: Check that commanding either contactor blocks the other and that the mechanical interlock independently prevents simultaneous closure. Typically the coil circuit uses the other contactor's NC auxiliary, such as 21–22, with the mechanical device fitted to the specified contactor pair. Perform isolated and approved functional checks without defeating the interlocks.

Read detailed article
16

Q16. How do you check the overload relay setting in a star-delta starter for its actual installation position?

Answer: Determine whether the relay senses motor line current or individual winding current before setting it. For a 30 A nameplate motor, a line-mounted setting may be 30 A and an inside-delta setting approximately 17.3 A, subject to manufacturer instructions. Trace the power connections and record the sensing position next to the setting.

Read detailed article
17

Q17. How do you choose contactor ratings and check motor-starter short-circuit coordination?

Answer: Select contactors by motor duty and circuit position and verify the tested short-circuit protection combination. AC-3 is usual for normal cage-motor switching, and IEC 60947-4-1 Type 1 or Type 2 coordination depends on the tested assembly and fault level. Check the exact manufacturer's coordination table against the installation's available prospective current.

Read detailed article
18

Q18. How do you monitor changeover current, voltage dips and transition behaviour during a supervised test?

Answer: Monitor changeover using authorised instruments that capture the brief current and voltage events during a supervised start. Record peak or RMS values with the mode clearly marked, and note the star time, transition interval and feeder voltage dip. Investigate significant spikes against load acceleration and the specified transition sequence before making adjustments.

Read detailed article
19

Q19. How do you check forward-reverse wiring, phase reversal and contactor interlocking?

Answer: Check that the reverse contactor swaps two supply phases and that both contactors cannot close at the same time. On a three-phase system, exchanging any two line phases reverses phase sequence, while the NC electrical and mechanical interlocks prevent a conflicting command. Confirm direction and safe stopping sequence under the authorised test procedure.

Read detailed article
20

Q20. How do you test Auto/Manual selector logic, emergency-stop circuits and external permissives?

Answer: Verify that the selector routes the intended command and that stop and safety functions operate in each required mode. Auto inputs may use 24 V DC, but the emergency-stop and reset behaviour must follow the approved safety design and cause-and-effect documentation. Test external permissives and check that resetting does not cause unintended restart.

Read detailed article

Test Your Knowledge Through Mock Test

Starter Practical – Part 2 · Two tests, 10 questions each. Choose a test below to begin.

Question 1 of 100 / 10 answered

Your answers stay on this page.

KEEP LEARNING WITH ELECTRICAL TOPIC

Learn Faster. Improve Your Electrical Skills.

WEBSITE • EMAIL UPDATES

New guides. Straight to your inbox.

Subscribe free. Get fresh website updates.

Have a question? Email info@electricaltopic.com

Videos in Hindi

Electrical Topic on YouTube

Watch practical electrical lessons from our YouTube channel.

Visit channel