Q1. What do you check before starting ACB or VCB maintenance?
Answer: Before ACB or VCB maintenance, confirm the work permit, switching plan, isolation boundaries and mechanical condition. The approved procedure covers primary and auxiliary sources, absence-of-voltage verification, required earthing and stored-energy release for the specific breaker. Have authorised staff cross-check the equipment identity and stop if the isolation state cannot be verified.
Q2. Why must the closing spring be discharged before maintenance?
Answer: Discharge the closing spring because it can move the mechanism suddenly even after electrical power is removed. Depending on the design, the stored-energy mechanism and charging motor require separate verification steps with a visible spring state indicator. Follow the maker's release procedure and verify the discharged state before touching mechanical parts under the permit.
Q3. How do you verify interlocking between two incomers and a bus coupler?
Answer: Interlocking prevents unapproved paralleling or energisation during an incomer and bus-coupler changeover. The approved two-incomer and one-coupler scheme may use electrical logic and trapped-key interlocks, with only the designed states permitted. Verify allowed and blocked states using the authorised test plan and record results without forcing a key or bypassing contacts.
Q4. What checks are needed before electrically closing an ACB or VCB?
Answer: Before closing, verify the breaker is in the specified position, protection is available and the closing permissives are satisfied. Check the declared control supply, such as 110 V DC where specified, and confirm charged spring and clear trip or interlock indications. Cross-check the switching schedule and resolve inconsistent feedback before issuing a close command.
Q5. What maintenance checks apply to an SF6 breaker and its gas monitoring system?
Answer: Check the SF₆ breaker for gas leakage, correct density indication and operation of the alarm and lockout functions. Compare temperature-compensated density and any required dew-point measurement with model-specific limits and the authorised gas service method. Have qualified personnel investigate abnormal trends and use approved recovery equipment when handling the gas system.
Q6. What readings and settings should be recorded after breaker maintenance?
Answer: Record electrical settings, mechanical condition, functional checks and test results needed to support return to service. Include test current in amperes, contact resistance in micro-ohms and opening or closing time in milliseconds when specified, plus control voltage and as-left settings. Compare the record with acceptance limits and document unresolved exceptions for sign-off.
Q7. How do you test a close coil circuit against the control drawing?
Answer: Trace the close command, permissives, coil and return against the approved wiring drawing before the functional test. Match the coil voltage and type, for example 110 V DC, and verify contacts in the ready-to-close path. Use the authorised test position and record the close indication and auxiliary feedback after the command operates.
Q8. How do you test a shunt-trip circuit without bypassing protection?
Answer: Check the shunt-trip circuit by using the approved test command through its designated path with protection available. Verify coil rating, battery voltage, trip circuit continuity and feedback as required by the wiring diagram, with DC ratings such as 24 V or 110 V on some models. Record opening and alarm results without bridging protective contacts.
Q9. How do you check undervoltage release supply and operation?
Answer: Check that the undervoltage release receives its specified supply and responds correctly when that supply is reduced or lost. Manufacturers give different operating, holding and drop-out voltage limits, so compare against the exact release rating and test procedure. Verify permissive restoration and breaker behaviour under the approved test configuration before re-energising the feeder.
Q10. How do you check a breaker after a short-circuit trip before restarting?
Answer: After a short-circuit trip, identify and clear the fault and assess the breaker before considering restart. Compare event current with the rated duty at the system voltage and review manufacturer post-fault inspection requirements for contacts, arc chutes and mechanism. Document the fault clearance and have the authorised person approve any return to service.
Q11. How do you check breaker interlocks before a bus-coupler changeover?
Answer: Before changing over a bus coupler, check that actual switch positions and the intended sequence match the approved interlocking logic. A trapped-key system releases or retains keys according to equipment state, while electrical permissives can verify auxiliary contact and supply conditions. Test the specified blocked states and escalate a discrepancy without defeating either system.
Q12. How do you document defects, repairs and retests at handover?
Answer: Handover records should describe each defect, the repair performed, acceptance criteria and the final retest evidence. Include breaker identification, as-found and as-left settings, instrument references and measured values such as operating time in milliseconds. Link results to work orders and obtain the required sign-off before releasing the breaker for service.